  1. Construction of Al-Juawaibiyah Regulating Tank at Nalut
  2. Oilfield Services at Ghani Oilfields
  3. Oilfield Services at Amal Oilfields
  4. Technical Services to LISCO
  5. Construction of Green Printing Press Complex
  6. Construction of Pump Stations & Turnout Headworks
  7. Construction of Accomodation Blocks
  8. Construction of Heavy Equipment Workshop
  9. Construction of 177 Farm Tanks
  10. Construction and repair of Amal Airport

Please Scroll down for project descriptions & status


Construction of Al-Juawaibiyah Regulating Tank at Nalut

DATE OF CONTRACT:

17 December 2007

CLIENT'S NAME:

Al Nahr Company (Fully owned by Great Man-made River Authority)

PROJECT VALUE:

USD 70 million

CONSTRUCTION WORK:

LD 996,478.000

PROJECT LOCATION:

Aljuwaibiyah, Gadames-Zwara-Al Zawiah Water System for Great Man-Made River project, Libya

PROJECT DURATION:

20 Months

PROJECT DESCRIPTION:

The work comprises of civil construction of 70,000 cubic meter capacity regulating tank with specialized formwork for columns, walls and roof panels. The work involved about 11850 cubic meters of concrete work and 2000 tons of rebar fabrication and installation. Work has been completed as per approved construction schedule.

team image

Oilfield Services at Ghani Oilfields for Harouge Oil Operations

DATE OF CONTRACT:

11 December 2007

PROJECT DESCRIPTION:

Electro-mechanical, mechanical, electrical and civil works at various stations at Ghani oilfields as follows; a. Preventive maintenance of Storage Tanks ST 222, ST 401, ST 701 and St 201 at Ghani & Zenad Stations.

team image

Oilfield Services at Amal Oilfields

DATE OF CONTRACT:

5 October 2007

PROJECT VALUE:

USD 2,550,000.00

PROJECT DESCRIPTION:

Preventive maintenance of Storage Tanks and Pipe Lines at various stations in Amal Oilfields as follows; a. Surge Tank, Settling Tank, and Gas Boot at Station 3 b. Surge Tank, Settling Tank, and Gas Boot at Station 7

team image

Provision of Technical Services to Libyan Iron & Steel Company

DATE OF CONTRACT:

20 February 2003

PROJECT VALUE:

USD 1,500,000.00/ year

PROJECT DESCRIPTION:

Provision of highly skilled Engineers, Specialists, Plant Operators and Technicians in the Operations Deptt, Maintenance Deptt, Direct Reduction Plant and the Flat Mill.

team image

Construction of Green Printing Press Complex

DATE OF CONTRACT:

8 March 1991

CLIENT'S NAME:

Libyan Investment Company, Tripoli, Libya.

PROJECT VALUE:

USD 57 millions

CONSTRUCTION WORK:

USD 6.2 millions

PROJECT LOCATION:

Sawani Road Tripoli, Libya

PROJECT DURATION:

24 Months

PROJECT DESCRIPTION:

Project Area 26,500 sq meters Portal frame building 6,300 sq meters Admn Building 1,680 sq meters Expert & workers residence, Warehouse, services building, compressor room, overhead & underground fire water tank, electrical control room, internal roads, water supply & sewage network, boundary wall.

team image

Construction of 2 Pump Stations and 3 Turnout Head Works

DATE OF CONTRACT:

11 April 2005

CLIENT'S NAME:

Al-Nahr Company (fully owned by The Great man-made River Authority)

PROJECT VALUE:

USD 48 millions

CONSTRUCTION WORK:

USD 2.1millions

PROJECT LOCATION:

Garabulli, Libya

PROJECT DURATION:

12 Months

PROJECT DESCRIPTION:

Pump Stations with an average area of 5,000 sq meters 6 meter deep. The 3 Turn out Head works are 3 meter deep below grade reinforced concrete structures with a control room on the ground floor. The project required approximately 5000 cubic meters of cast in place concrete and approximately 600 Tons of Steel reinforcements

team image

Construction of North Accommodation Blocks

DATE OF CONTRACT:

21 April 2003

CLIENT'S NAME:

Veba Oil Operations

PROJECT VALUE:

USD 4,150,000.00

PROJECT LOCATION:

Amal Oilfields, Libya

PROJECT DURATION:

2 years

PROJECT DESCRIPTION:

The scope of work comprised of design and construction of five new accommodation blocks at AMAL oil field. In addition to the structural design and construction of buildings, the work also included design and installation of HVAC system, telephone, electrical, general and emergency lighting, sanitary and waste water system, potable water system, fire water, fire fighting and fire alarm systems.

team image

Construction of Heavy Equipment Workshop

DATE OF CONTRACT:

15 March 2005

CLIENT'S NAME:

Veba Oil Operations. (Petro Canada)

PROJECT VALUE:

USD 1,290,000.00

PROJECT LOCATION:

Ghani Oilfields, Libya

PROJECT DURATION:

12 Months

PROJECT DESCRIPTION:

The project comprises of a 7.5m eaves height steel structure building with 22m span and two overhead cranes. The lean to section comprises of engine repair workshops, stores, kitchens, washrooms and offices. The facility is equipped with oil dispensers, tyre repair facilities, compressed air network, vacuum suction network, fire alarm systems, smoke alarm systems and fire fighting facilities.

team image

Construction of 177 Farm tanks at Tarhuna

DATE OF CONTRACT:

10 May 2001

CLIENT'S NAME:

Al-Nahr Company Limited (Fully owned by The Great Man-Made River Authority)

PROJECT VALUE:

USD 1,969,000.00

PROJECT LOCATION:

Tarhuna, Libya

PROJECT DURATION:

24 Months

PROJECT DESCRIPTION:

The project comprises construction of 177 farm tanks for the water supply and irrigation network. The tanks are made of reinforced concrete, 300mm thick walls and are cast in place at various locations along the network.

team image

Construction and repair of Amal Airport

DATE OF CONTRACT:

10 May 2001

CLIENT'S NAME:

Veba Oil Operations. (Petro Canada)

PROJECT VALUE:

USD 1,110,000.00

PROJECT LOCATION:

Amal Oilfields, Libya

PROJECT DURATION:

12 Months

PROJECT DESCRIPTION:

The project comprises construction and repair of an airport at Amal oilfields. Modifications were also done to the Aviation Fuel system. The repair work included rehabilitation of the existing runway strip, 7000 meters of crack widening, routing and filling with specially designed sealant, milling and dispensing machines for extreme climates.